Asphalt Pavement Improvement on Highway No. 325, Samut Songkhram Province
โพสต์เมื่อ : 20 มี.ค 2568 เวลา 1:21 น.
| Project Name | Improvement of the existing asphalt concrete pavement using in-place recycling on Highway No. 325, Control Section 0102, Bang Phrom - Samut Songkhram Section, between Km. 39+450 to Km. 40+630 (Left & Right sides), with a total work quantity of 30,791 square meters. |
| Location | Samut Songkhram Province |
| Project Owner | Samut Songkhram Highway District |
| Contract No | สส 16/2568 |
| Contractor | HEMARAT CONSTRUCTION CO., LTD. |
| Project Value | 15,000,000 |
| Project Duration | 7 February 2025 - 22 April 2025 |
| Project Scope | The repair and rehabilitation of asphalt pavement by applying heat to soften the existing material, then using specialized machinery to mill the existing surface and reuse the material within the same process is called **Asphalt Hot-Mix In-Place Recycling**. |
| Project No | 67119423090 |